Skip to main content
Skillvault

SKV-CMA-1060

Estoppel, Waiver and Conduct: When Practice Overtakes the Contract

Currently available for free preview

00:23:21·advanced·3 lessons

Contract ManagementClaims ManagementContract Administration

Currently available for free preview

About this course

A short, practice-led course on what happens when the way a construction project is actually run begins to diverge from what the contract says.

Construction contracts prescribe formal procedures. Projects often develop their own working practices. Instructions are given during site walks, verbal directions are followed, short emails replace formal notices, and work proceeds on the understanding that the commercial position will be resolved later.

The difficulty comes when the project reaches final account and one party decides to insist on the written contract.

This course develops a practical discipline for understanding the gap between contractual form and actual conduct. It explores how repeated behavior, representations, reliance, elections, and prevention can affect the positions parties take when contractual formalities have not been followed.

The Case

The course follows Oakshaw Joinery, delivering a $4.1M joinery and external-envelope package for the Halden Building.

The contract requires written variations on the employer's prescribed form and contractor notice within 28 days as a condition precedent.

But the project developed differently.

Weekly site walks became the forum for instructions. Verbal directions were followed by short emails. The recurring message was:

"Proceed, we'll sort the money later."

Thirty-one instructions followed. By final account, $1.48M of additional work has been executed, but none of the required formal notices has been served.

A new quantity surveyor now allows only $210K.

With the project term just 11 weeks away and delay damages at $18,500 per week, the contractual argument has become a live commercial problem.

The question is not simply what the contract says.

It is what the parties actually did, what the record can establish, and what position can now responsibly be taken.

Three Lessons

Lesson 1 — When Conduct Rewrites the Contract

Examine the tension between written requirements and project practice. Learn how repeated conduct, representations, instructions, and acceptance of performance can create arguments around waiver and estoppel—and where the limits of those arguments lie.

Lesson 2 — Weighing the Course-of-Dealing Record

Move from principle to evidence. Assess site diaries, photographs, emails, instruction trails, and meeting records. Examine why some instructions are strongly supported while others depend largely on diary evidence. The lesson also considers waiver by conduct, nomination, and the authority of site personnel.

Lesson 3 — Election, Prevention and Papering the Conduct

With the project under time pressure, examine election and prevention and decide how the parties should respond. The focus then turns forward: what should be asserted, what should be reserved, and how should the agreed position be documented so the same uncertainty does not continue?

What You Will Learn

By the end of the course, you will be able to:

  • Distinguish contractual requirements from actual project conduct.
  • Identify potential waiver and estoppel arguments.
  • Assess reliance, repetition, knowledge, and subsequent performance.
  • Weigh the strength of contemporaneous project records.
  • Consider the authority of personnel giving instructions.
  • Understand the practical significance of election and prevention.
  • Separate a persuasive project narrative from what the evidence can support.
  • Paper the position clearly for the work that remains.

What This Course Is Not

This is not legal advice or a jurisdiction-specific treatment of a live dispute. It is not a textbook course on land-law estoppel, criminal waiver, or civil evidence procedure.

Instead, it provides a practical construction-contract discipline:

read the contract → examine the conduct → weigh the record → decide the position → paper it forward.

By the end, you should be able to recognize when a project has drifted away from its contractual process—and make a more disciplined judgment about what that conduct means, what can be proven, and what should happen next.

What you will cover

  1. 01When Conduct Rewrites the Contract

  2. 02Weighing the Course-of-Dealing Record

  3. 03Election, Prevention and Papering the Conduct