The module ''6.4 Compound Question Battery'', the exercise PSP-MC-03CP-01. what's the critical path.

Ashutosh Maurya, PMP, CCP, PSP The critical path duration is 30 day. Critical path passed through A-B. 25 day (activity A) + 5 days FF to lag (B is FF+5 to A) 10 months ago
loader
loader
Attachment
Ashutosh Maurya, PMP, CCP, PSP Sure, can you please mail me screenshot of both the questions? For some reason I am not able to identify the questions. 10 months ago
loader
loader
Attachment
Keight Navarro Ok, I would send the screenshot of both questions. 10 months ago