Can someone explain the answer to Question 2 of the Lesson 2.3 Quiz?

A network diagram consists of 5 activities - A to E. Critical path is B-D-E. Cost...
Show more

A. Cheyenne Ladd Thank you for confirming. Its seems there have been a handful of errors throughout the early lessons. 5 months ago
loader
loader
Attachment
Gian B. Schedule Compression Cost = 2(2700)+1(3000)+1(5000)=$13400 3 weeks ago
loader
loader
Attachment
Gian B. Calculated using this solution, 2(2000)+1(3000)+1(5000)=$13400 3 weeks ago
loader
loader
Attachment

Question about WBS / OBS / CBS : is cost account is include in a control account ? As we understand control account is "larger" tha jus a cost... Show more

Question MC060 : with AACE standard start day = 1 duration = EF - ES +1 but on the test EF - ES +1 = 7 but the correct answer is said to be 6

Question MC082 : characteristic of PDM vs ADM : why the answer "uses arrows to signify logic in a network" is not also a correct answer ?

Ashutosh Maurya, PMP, CCP, PSP Let me check. Can you please send me screen shot of the question on my mail id and I will review and respond as time permits. 7 months ago
loader
loader
Attachment
Fabien Barcelo OK ! 7 months ago
loader
loader
Attachment

Questions about AON AOA PDM PERT :
1) Is PDM always a AON ?
2) Is a PERT always a AOA ?

Ashutosh Maurya, PMP, CCP, PSP 1) Is PDM always a AON ? - Yes
2) Is a PERT always a AOA ? - Generally Yes.As the PERT diagram has only a “Finish to Start” relationship.
7 months ago
loader
loader
Attachment
Fabien Barcelo Thanks ! 7 months ago
loader
loader
Attachment

Question : in PSP study guide on page 254 Appendices A there is a example of diagram with calendar date (which is more complex with the week-end)... Show more

Abdul Abdul FABIAN, PLEASE, EMAIL ME FROM YOUR PERSONAL ACCOUNT AT AWAJID2010@GMAIL.COM 7 months ago
loader
loader
Attachment
Ashutosh Maurya, PMP, CCP, PSP Yes.. but in that case you will have calendar provided in the exam. 7 months ago
loader
loader
Attachment
Fabien Barcelo Ok thanks !! 7 months ago
loader
loader
Attachment

Questions about sections 3.4 3.5 :
1) why owner is a external stakeholder to project ?
2) what's the difference DB and EPC ? It's seems to be close.

Mohamed Idlbi likes this.
Fabien Barcelo My colleague explained that owner is external because the PM can't control it. 7 months ago
loader
loader
Attachment
Ashutosh Maurya, PMP, CCP, PSP DB and EPC are similar when it comes to obligations/roles and responsibilities of the contractor. However, the term DB is used in building... Show more 7 months ago
loader
loader
Attachment
Fabien Barcelo Thanks ! 7 months ago
loader
loader
Attachment

In section 2.5 Risk management on the last slide it is said : "qualitative method includes simulation, sensibility analysis and decision tree"... Show more

Ashutosh Maurya, PMP, CCP, PSP Yes you are right. These are Quantitative methods. 7 months ago
loader
loader
Attachment
Fabien Barcelo Thanks ! 7 months ago
loader
loader
Attachment

Few questions
1) Difference between consumed and incurred cost (in EVM) ?
2) ADM and CPM : is it possible to calculate a CPM with a ADM ?
3) PDM and CPM...
Show more

Question : how much time is recommend for the memo question ?

Ashutosh Maurya, PMP, CCP, PSP A very few PSP test takers have provided feedback as exam time was less to complete all the questions. Now answering to your query, 30-40 minutes... Show more 8 months ago
loader
loader
Attachment
Fabien Barcelo thanks ! 8 months ago
loader
loader
Attachment
Fabien Barcelo thanks ! 8 months ago
loader
loader
Attachment

Hello I start the course and I plan to pass the exam next june

Abdul Abdul posted a new discussion11 months ago

Compound Question #1

As per given detail in the Compound Question #1, the answer should be 16 but as per the given answers it is 22. Please, can any one explain how?...

AA-1020-IL Planning and Scheduling Professional (PSP) Review Course

I am interested to take an exam AACE PSP certification.


May I know your course AA1020: Planning and Scheduling Professional (PSP) can help me to take...
Show more

santhosh Palaniappan likes this.
Ashutosh Maurya, PMP, CCP, PSP Hey Santosh, We have a good track record of students passing through Protrain course. For any query please write me ashutosh.maurya@protrain.com 1 year ago
loader
loader
Attachment

Are there any materials for the course to read from

Ashutosh Maurya, PMP, CCP, PSP Hey Hassan, as such we don't have reading materials. However, please let me know what are you looking for? 2 years ago
loader
loader
Attachment

the video for section 4.2 Schedule Development, Maintenance & Control is not working with me

Ashutosh Maurya, PMP, CCP, PSP 4.2 Schedule Development, Maintenance & Control are covered in lecture 4.1 3 years ago
loader
loader
Attachment

Please there is no tutorial video for Schedule Development, Maintenance & Control. I need help.

Ashutosh Maurya, PMP, CCP, PSP The contents are covered in lecture 4.1 3 years ago
loader
loader
Attachment
Ronald Castillon Hi Ashutosh, do you have another sample of Memo exam? 3 years ago
loader
loader
Attachment

Question 17 in the compound questions

where is activity C in the table?

Salem no reply 4 years ago
loader
loader
Attachment

Question 10 in the compound questions says that:

what is the normal total cost of the project? the answer was given by multiple critical path...
Show more

Salem likes this.
Salem posted a new discussion4 years ago

Compound Question Battery Connect Here

Question no 9 in compound questions battery (PSP-MC-02CP-01) How can I create the network without predecessor but only nodes?

AA-1020-IL Planning and Scheduling Professional (PSP) Review Course