Risk Management Question
Available Files
No files uploaded.
Related discussions
- Schedule Compression - 2.3: Quiz: Question 5 Thank you. Could you please double check the question? I think there may be a typo. There is a reference to Activity A when I believe it should...
- Compound Question Battery Connect Here
- Compound Question #1
Replies
Ashutosh Maurya, PMP, CCP, PSP
This is a tricky question. Let us solve by an elimination process. ‘A. Corrective action’ is a Quality Management process, so not right choice. ‘B...This is a tricky question. Let us solve by an elimination process. ‘A. Corrective action’ is a Quality Management process, so not right choice. ‘B. Risk management plan’ tells about how the Risk shall be managed in the project. It is not an approach. ‘C. Workaround’ is performed to mitigate the Risk when the Risk event occurs.
Now choice D. When we identify a Risk we follow two approaches - 1. Avoid it - don’t engage in such business. 2. Accept it and then work on Risk response development. So, D is the most appropriate choice.
Show more 6 years ago
Now choice D. When we identify a Risk we follow two approaches - 1. Avoid it - don’t engage in such business. 2. Accept it and then work on Risk response development. So, D is the most appropriate choice.
Show more 6 years ago




Risk response development will use which of the following approaches?
A. Corrective action
B. Risk management plan
C. Workarounds
D. Acceptance